|  | Design 
                                          of auxiliary buildings | 
                                       
                                        |  | Stanchion/beam 
                                          design from reinforced concrete sections, 
                                          gable roof of prefabricated battens, 
                                          hipped roof; non-bearing exterior walls 
                                          and roof covering in sandwich elements 
                                          consisting of two layers of profiled 
                                          aluminium sheet with polyurethane insulating 
                                          material, D = 6.0 cm | 
                                       
                                        |  | Project 
                                          data | 
                                       
                                        |  | Floor 
                                          space : Construction costs: 2.40 Mio Period: 
                                          1997 / 1198
 | Cubical 
                                          content : Work phases HOAI: 1 - 9
 Construction time: 3 / 97 - 12 / 97
 | 
                                       
                                        |  | Builder-owner | 
                                       
                                        |  | Wasser 
                                          Nord GmbH & Co KG, Gewerbepark 5-7, 16540 Hohen Neuendorf
 |