Design of auxiliary buildings
Stanchion/beam design from reinforced concrete sections, gable roof of prefabricated battens, hipped roof; non-bearing exterior walls and roof covering in sandwich elements consisting of two layers of profiled aluminium sheet with polyurethane insulating material, D = 6.0 cm
Project data
Floor space :
Construction costs: 2.40 Mio Period: 1997 / 1198
Cubical content :
Work phases HOAI: 1 - 9
Construction time: 3 / 97 - 12 / 97
Builder-owner
Wasser Nord GmbH & Co KG,
Gewerbepark 5-7, 16540 Hohen Neuendorf